Construction Update March 3

The Joan and Paul Waechter Welcome Centre at Headwaters Health Care Centre

What happened for the weeks of (March 2 & 9)
  • The construction hoarding/barriers will be removed tonight (March 3)
  • There will be temporary barriers in place and the space will not be fully accessible until early next week because there is still some flooring work underway
  • The final installation and testing of equipment is also underway this week
  • The new exterior patio door is being installed
What to expect on March 9
  • Patient Accounts will be relocated to the main lobby. The office on the main floor will be closed.
  • The Cafe, Gift Shop and new staircaase will be accessible and open.
  • The Switchboard construction will be complete.
HN Construction hours of operation
HN Construction and several sub-trades will continue working on the finishes as part of the final stages of construction completion in addition to removing the hoarding tonight (March 3).
 
Construction Benefits
Headwaters patients and their families will experience a new one-stop shop with respect to arrival, registration and bill payment, supported by self-service kiosks and centralized registration.

The lobby will include a new, more accessible entryway, a new information desk, expanded waiting areas, a therapeutic and fully accessible outdoor space, a re-designed gift shop and café and a new safer and more accommodating central staircase.

These renovations are being funded through donations to the Headwaters Health Care Foundation and the Headwaters Health Care Auxiliary.

The lobby and main entrance will be named The Joan and Paul Waechter Welcome Centre, in honor of local residents, Joan and Paul Waechter’s cumulative giving to Headwaters Health Care Centre.