Construction Update December 13

The Joan and Paul Waechter Welcome Centre at Headwaters Health Care Centre

What happened last week (December 6 - 13)
  • The construction team is continuing to complete the new stairwell.
  • The drywall painting also continues.
  • Some hoarding went up in the corridors of the lower level for the construction team to access heating units for the lobby. These will be in place for about another week.
What to expect
  • HN Construction will continue installing the new stairwell.
  • HN Construction will have hoarding up in the lower level areas to access heating units.
  • Extra hoarding in hallways on the lower level between Dec 13 – 20, 2019.
HN Construction hours of operation
The construction crew and the sub-trades work on site 6:00am to 5:00 pm Monday through Friday and sometimes on the week-ends (but with advanced notice).
 
Construction Benefits
Headwaters patients and their families will experience a new one-stop shop with respect to arrival, registration and bill payment, supported by self-service kiosks and centralized registration.

The lobby will include a new, more accessible entryway, a new information desk, expanded waiting areas, a therapeutic and fully accessible outdoor space, a re-designed gift shop and café and a new safer and more accommodating central staircase.

These renovations are being funded through donations to the Headwaters Health Care Foundation and the Headwaters Health Care Auxiliary.

The lobby and main entrance will be named The Joan and Paul Waechter Welcome Centre, in honor of local residents, Joan and Paul Waechter’s cumulative giving to Headwaters Health Care Centre.

Questions about Construction?
Please feel free to email info@headwatershealth.ca if you have questions about the improvements underway at your local hospital.